2/10/12 UPDATE: Cobo Transformation Construction Schedule

On Time; On Budget

Cobo Center

Capital Improvement Program 2010-2015

BROAD PROGRAM OBJECTIVES

To increase the competitiveness of Cobo Center in the highly competitive market for conventions, conferences, trade shows and other special events that have a large, positive economic impact on the Detroit regional economy.
To revitalize Cobo Center, including updated image.
To make Cobo Center financially viable.

DETAILED PROGRAM OBJECTIVES
1. To significantly improve Cobo Center’s customer experience.
2. To improve Cobo Center’s customer service.
3. To reduce Cobo Center’s customer costs.
4. To ensure greater reliability in Cobo Center’s systems and operations.
5. To enhance life safety and security.
6. To improve operational efficiency and thereby reduce operational costs.
7. To accomplish significant energy savings for the national benefit.
8. To make significant progress towards a “Green” building and “Green” operations.
9. To promote asset protection and preservation.
10. To establish a meaningful relationship with the immediate district and downtown activities.


CAPITAL IMPROVEMENT PROGRAM PHASES
Phase I: $3 million budget                                                                       Completed 12/09
Phase I exhibition electrical power improvements.
Roof leak reduction.
Exhibition hall wet floor box leak reduction.
Completed on schedule and on budget by NAIAS 2010

Phase IIa: $21 million budget                                                                   Completed 12/11
Infrastructure improvements.
Support for NAIAS 2011.
NAIAS 2011 projects completed on schedule.

Phase IIb: $28 million budget                                                                   Completed 12/11
Five projects:
o Enclosure of loading dock.
o Phase II exhibition electrical power improvements.
o Creation of 400 parking spaces under Detroit Hall.
o Addition 22,500 gross square feet of exhibition space.
o Partial reroofing of building.


Phase III: $227 million budget                                                                            In Process
Combination of major physical changes and continuation of
infrastructure improvements:

1. Infrastructure improvements continuing work from Phase IIa including:
• Parking system improvements
• HVAC improvements including further efficiency enhancements, improved controls, etc.
• Plumbing changes including low flow fixtures.
• Fire protection enhancements including fire protection extension throughout all areas and system upgrades
• Electrical testing and correction of deficiencies.
• Special system upgrades including enhanced CCTV system and communications system

 

2. Development of Cobo Arena as new 38,000 sq. ft. ballroom.................................................Complete 4/13
  with meeting rooms underneath. Major features include:
• Seating capacity: 2,375 for dining and 3,800 for general sessions.
• Ballroom capable of subdivision into smaller units.
• Ballroom overlooks Hart Plaza.
• Entry to ballroom area directly from Jefferson Avenue.
• Exterior terrace overlooking Detroit River and Hart Plaza.
• Hydraulic lift stage directly into Ballroom capable of
raising automobile.
• New kitchen serving both ballroom and new
food court............................................................................................................. complete 5/13
• Pre-function space overlooking Detroit River............................................................ complete 9/13
• Pre-function space overlooking new signature
atrium space........................................................................................................... complete 12/13
• Up to six meeting/breakout rooms below ballroom..................................................... complete 1/13

 

3. Creation of Atrium connecting main concourse to river and ...................................... complete 1/13
opening lower level/Michigan Hall to main level space. Major
features include:
• Creates a central “signature” space.
• Opens views from main level concourse directly to Detroit River.
• Creates route from main concourse down to Detroit riverfront.
• Creates second major entrance from Civic Center Drive into building and up to main concourse.
• Connects main level exhibition space with lower level Michigan Hall exhibition space.
• Improves viability of lower level spaces.

 

4. Renovation of south side constructed in 1960 and not ......................................................complete 1/13
included in 1989 upgrade. Major features include:
• Approach to south side from main concourse area through new “signature” atrium space.
• Creation of pre-function space overlooking Detroit River through new glazed exterior wall
• Configuration with back-of-house spaces allowing materials handling to new south side spaces and to new materials handling service areas on east side minimizing interface with public areas.
• New food service support areas
• Lower level opened up south of Michigan Hall as extension of concourse system.
• New glazed wall along south side of lower level opening area to Detroit riverfront.
• Much improved entrance experience from Civic Center Drive curbside drop-off.
• Reconfiguration of rentable space into new
appropriately sized meeting rooms directly off
pre-function space. ......................................................................................................complete 12/13

 

5. Upgrade of east side main concourse and adjacent....................................................... complete 12/14
spaces. Major features include:
• Reconfiguring rentable and non-rentable spaces to locate rentable spaces in prime locations
• Upgraded concourse finishes and lighting
• Upgraded rentable space finishes
• Minimization of service traffic in public areas by addition of “back-of-house” service corridors.
• Widening of concourse by elimination of some escalators.
• New food court and improved concession spaces.

6. New east side exterior skin with video wall. Major ..........................................................complete 2015
features include:
• Upgraded appearance for new image.
• Creation of canopy to provide weather protection for main entrance.
• Addition of “media mesh” to allow dynamic images of Cobo Center events on exterior.

Total Capital Improvement Budget: $279 million


Facebook: http://www.facebook.com/pages/Detroit-Regional-Convention-Facility-Authority/176937915684921

PR Contact: Twitter: @CoboAuthority Website: www.drcfa.org
Tom Constand
starrconstand business communication
(313) 964-4447
(248) 417-4119 cell
tconstand@starrconstand.com
                                                                     # # #
 

DRCFA Contact Information
Detroit Regional Convention Facility Authority
1 Washington Blvd, Suite 401
Detroit, MI 48226
Phone: 313-877-8777

Media Inquires

All media inquires should be directed to Tom Constand.
Phone: 248-417-4119
Email: tconstand@starrconstand.com